How Slow Supply Chains Affect Senior Living Operators: Improving, Upgrading, or Developing New Inventory

More Than Just Inconvenient, Supply Chain Issues Present a Serious Threat to Operator Survival.

Supply chain delays have created a compounding crisis for senior living operators at precisely the wrong time—when demand is surging and existing inventory is aging. Here’s how these delays cascade through every aspect of development, renovation, and improvement.

THE PERFECT STORM: CURRENT CONTEXT
Construction costs for new senior living units continue to rise as materials and labor remain expensive, while a big development rebound is unlikely for 2025, exacerbated by inaccessibility to financing as lending remains a barrier to new growth.

The result:
The third quarter of 2024 saw the fewest spaces under construction since 2014.

1. NEW DEVELOPMENT: DELAYS THAT KILL PROJECTS

Extended Lead Times for Critical Equipment
Emergency generators can have wait times of more than a year, while lead times typically run 6-9 months for steel products like joists and decking and 4-8 months for roofing materials.

Senior living-specific impacts:
– HVAC systems: 6-12 months for specialized air handling units with infection control requirements
– Commercial kitchen equipment: 4-8 months for industrial ovens, walk-in refrigerators, dishwashers
– Elevators: 8-18 months (critical for multi-story facilities)
– Nurse call systems: 3-6 months for integrated communication technology
– Fire suppression systems: 6-10 months for code-compliant systems
– Generators and backup power: 12+ months (required for life safety)

Cascading Schedule Impacts:
Lead times in the US market continue to experience delays of 2 or 3 times the pre-pandemic timetables.

What this means:
– A project planned for 18-month completion now takes 24-36 months
– Carrying costs accumulate: construction loans, insurance, property taxes
– Financial model deterioration: Every month of delay adds $100K-500K+ in costs
– Market conditions change during extended timelines, affecting pro formas
– Competitors may open first, capturing market share

Financing Complications

The domino effect:
– Delays extend construction loans beyond original terms
– Interest rate exposure increases (especially problematic in rising rate environments)
– Extension fees and penalties accumulate
– Lenders lose confidence, making refinancing difficult
– Equity partners become frustrated, potentially pulling funding
– Projects stall or fail mid-construction

Procurement Strategy Nightmares

Construction components that involve long lead times will often require the approval of production drawings before ordering, thereby adding to the lead time and causing further delay.

Operators must:
– Order equipment 12-18 months before installation (risky if project delays occur)
– Pay deposits far in advance, tying up capital
– Warehouse materials on-site (theft risk, weather damage, storage costs)
– Accept spec changes mid-project if original items become unavailable
– Navigate approval processes with multiple stakeholders before ordering

2. RENOVATIONS AND UPGRADES: THE HIDDEN CRISIS

Operational Disruptions

Unlike ground-up construction, renovations occur in occupied buildings with residents. Supply chain delays create:
– Extended disruption periods: A 3-month renovation becomes 6-9 months
– Resident dissatisfaction: Noise, dust, limited access to amenities
– Move-outs during construction: Revenue loss from units taken offline
– Staff stress: Operating through ongoing construction
– Safety concerns: Increased fall risks, construction hazards near vulnerable populations

Phased Renovation Complications

The compounding problem:
– Renovations must be phased to keep facilities operational
– Each phase depends on previous phase completion
– Material delays in Phase 1 cascade through all subsequent phases
– 12-month project becomes 24-30 months
– Total revenue impact: Losing $50K-150K per month in offline units

Equipment Replacement Challenges

Critical systems operators can’t wait for:
– Failing HVAC units: Can’t wait 9 months; must pay premiums for expedited delivery or accept inferior substitutes
– Kitchen equipment failures: Must source alternatives immediately, often at 30-50% markups
– Water heaters, boilers: Life safety issues require emergency procurement
– Fire alarm systems: Code violations if not operational

Result:
Operators pay 2-3x normal costs for emergency replacements or accept downtime/compliance violations.

Aesthetic Upgrade Complications

Even cosmetic improvements face delays:
– Flooring: 8-16 weeks for specialized slip-resistant, antimicrobial products
– Furniture: 12-20 weeks for commercial-grade, healthcare-appropriate pieces
– Window treatments: 6-12 weeks for fire-rated, light-blocking materials
– Fixtures: 8-12 weeks for ADA-compliant, senior-friendly hardware

Impact:
Dated, institutional-looking facilities can’t compete with newer properties for discerning Baby Boomer residents.

3. DEFERRED MAINTENANCE ACCELERATION

The Vicious Cycle

Supply chain delays force operators to defer maintenance:
– Equipment breaks: Order replacement with 6-month lead time
– Temporary fixes: Duct tape and prayers while waiting
– Multiple breakdowns: Other equipment fails during wait
– Emergency repairs: Pay premiums for immediate solutions
– Budget exhaustion: No funds left for planned upgrades
– Facility deterioration accelerates

Compliance Risks

Regulatory requirements don’t pause for supply chain issues:
– Fire code violations: Can’t wait 12 months for fire panel replacement
– Health code failures: Kitchen equipment must meet standards
– ADA compliance: Broken accessibility features must be fixed immediately
– Licensing jeopardy: Some states won’t renew licenses with outstanding violations

Operators caught between: Compliance requirements, unavailable equipment, and insufficient budgets.

Senior Living Tech Advisory Services - Ideas

SCHEDULE A DISCOVERY WITH A SENIOR LIVING TECH ADVISOR

“We brought in TekEfficient for tech expense management analysis to see if we had waste across our IT portfolio. Turned out we did and a free consultation turned into 40% in savings we used to fund innovation and upgrades.”

Let’s Talk

4. COMPETITIVE DISADVANTAGE

The Amenities Arms Race

Modern senior living residents (Baby Boomers) expect:
– Resort-style amenities
– Smart home technology
– Wellness centers with professional equipment
– Upscale dining venues
– Spa and salon services

Supply chain reality:
– Fitness equipment: 4-8 months
– Commercial spa equipment: 6-10 months
– Smart building systems: 8-12 months
– High-end kitchen upgrades: 6-12 months

Result:
Operators can’t compete with newer facilities while waiting for upgrades, losing residents to competitors.

Technology Infrastructure Gaps

The pandemic accelerated technology adoption:
– Telehealth capabilities
– Digital engagement platforms
– Smart monitoring systems
– Electronic health records

Supply chain bottlenecks:
– Networking equipment: 3-6 months
– Servers and infrastructure: 4-8 months
– Integrated systems: 6-12 months for custom solutions
– Installation/integration: Skilled labor shortages extend timelines

Competitive impact:
Facilities without modern technology lose tech-savvy residents.

5. FINANCIAL IMPLICATIONS

Cost Escalation

If materials arrive late, construction may be delayed, leading to extended project timelines and increased labor costs.

The cost cascade:
– Material price increases: Prices rise while waiting; a $1M HVAC system ordered in 2024 costs $1.3M by 2025
– Labor cost inflation: Construction crews idled during delays must be paid or reassigned (losing them)
– Carrying costs: Every month of delay costs $100K-500K in financing, taxes, insurance
– Opportunity costs: Capital tied up in delayed projects can’t be deployed elsewhere
– Revenue loss: Delayed openings mean no resident revenue

Pro-Forma Destruction

Original underwriting assumes:
– 18-month construction timeline
– Predictable costs
– Timely stabilization and cash flow

Supply chain reality:
– 30-month actual timeline
– 20-40% cost overruns
– Delayed stabilization by 12+ months
– IRR destruction: Projects that penciled at 12% IRR now deliver 6-8%

Financing Market Exit

Lenders and investors respond:
– Higher equity requirements (35-40% vs. 25-30% pre-pandemic)
– Stricter underwriting standards
– Contingency reserves increase from 5% to 10-15%
– Some lenders exit senior living development entirely

Result:
Lending remains a barrier to new growth.

6. STRATEGIC PARALYSIS

The Wait-or-Act Dilemma

Operators face impossible choices:
Option A: Move forward with development/renovation
– Risk: Extended timelines, cost overruns, market changes
– Reality: Necessary to remain competitive

Option B: Wait for supply chains to normalize
– Risk: Falling further behind, losing market share
– Reality: No indication when “normal” returns

Option C: Smaller, incremental improvements
– Risk: Doesn’t solve obsolescence problem
– Reality: Kicking the can down the road

Decision Paralysis

If procurement processes are delayed, the arrival of critical materials may be postponed, slowing down construction progress and requiring adjustments in labor scheduling and other project phases.

Impact:
Operators delay critical decisions while trying to predict unpredictable supply chains, causing missed opportunities.

Senior Living Tech Portal - icon

GET MORE SENIOR LIVING TECH INFORMATION

Check out the TekEfficient Senior Living information portal complete with rankings, links, resources and more. Have more questions? Contact an advisor.

Visit our SL Portal

7. MARKET SUPPLY CRISIS

The Macro Problem

A $275 billion investment gap in senior living development across the country by 2030 means there won’t be enough housing to meet the demand of older adults in the next five years.

Declining trend of new construction starts in 2023 and continuing in 2024 will result in a corresponding decrease in new inventory being delivered to market starting in 2025.

Demand continues accelerating (80+ population growing 47% over next decade). Supply can’t catch up even if financing improved today.

Result:
Severe housing shortage for seniors, reduced access to care.

8. OPERATIONAL WORK-AROUNDS AND THEIR COSTS

What Operators Are Doing

Emergency procurement strategies:
– Over-ordering: Buying equipment for future phases early (capital tied up, storage costs, obsolescence risk)
– Alternative sourcing: Accepting inferior substitutes to avoid delays
– Premium payments: Paying 30-50% markups for expedited delivery
– International sourcing: Looking overseas (longer shipping, customs complexity, quality concerns)
– Used equipment: Buying refurbished items (shorter lifespan, warranty issues)

Renovation adaptations:
– Smaller phases: Breaking projects into tiny increments (inefficient, higher costs)
– Temporary facilities: Portable kitchens, temporary HVAC (expensive, disruptive)
– Extended resident relocations: Moving residents to hotels during major work (expensive, unpopular)
– Cost of workarounds: 20-40% premium over normal construction/renovation costs.

9. LABOR SHORTAGE INTERSECTION

Supply chain delays intersect with skilled labor shortages.

The compounding crisis:
– Idle crews: Workers wait for materials; must be reassigned or lose them
– Stop-start construction: Inefficient; productivity drops 30-50%
– Compressed schedules: When materials finally arrive, crews rush to catch up (quality issues)
– Specialty trade availability: Elevator technicians, HVAC specialists book months ahead; delays cause missed windows
– Cost escalation: Must pay premiums to retain crews during delays

Senior living-specific challenge:
Healthcare construction requires specialized trades familiar with infection control, life safety codes, and senior-specific requirements—even scarcer than general construction labor.

10. STRATEGIC RESPONSES

What Smart Operators Are Doing

Long-term procurement planning:
– Identifying long-lead items 18-24 months before need
– Building relationships with multiple suppliers
– Negotiating allocation agreements for critical equipment
– Maintaining pre-approved equipment specifications for quick ordering

Design flexibility:
– Specifying multiple acceptable equipment brands
– Designing for adaptability (easy to swap components)
– Pre-approving substitutions with regulators/stakeholders

Financial strategies:
– Building 15-20% contingency reserves (vs. 5-10% historically)
– Extending project timelines in pro formas (30-36 months vs. 18-24)
– Negotiating flexible financing with built-in extension options

Alternative development models:
– Adaptive reuse (converting hotels, office buildings—shorter timelines)
– Modular/prefab construction (factory-built, less supply chain exposure)
– Smaller facilities (easier to build, faster to market)

The Bottom Line

Slow supply chains create a multi-layered crisis for senior living operators:
– New development becomes financially unviable for many operators
– Existing inventory ages faster than it can be renovated
– Competitive gaps widen between modern and outdated facilities
– The industry-wide supply shortage worsens, creating access crises
– Only the largest, best-capitalized operators can navigate the complexity

The ultimate impact:
Senior living owners and operators in 2025 will need to navigate the potential impacts of increased tariffs and changes in immigration and healthcare policy, suggesting supply chain pressures may intensify before they improve.

For the senior living industry, supply chain delays aren’t just an operational inconvenience—they’re an existential threat that’s accelerating facility obsolescence, widening the supply-demand gap, and fundamentally reshaping which operators can survive and thrive in the coming decade.

 

 

TekEfficient can help. Our Technology Procurement Services save you time and money allowing you to focus on what matters most.

TEKTOOLS: SENIOR LIVING
REMOTE WORK TECH CHECKLIST

Assisted Living Tech Resource - Remote Work Tech Checklist

TEKEFFICIENT OVERVIEW:
SENIOR LIVING TECHNOLOGY ADVISORS

Assisted Living Tech Brokers - TekEfficient Overview

SENIOR LIVING TECH RESOURCE:
SETTING YOUR DIGITAL FOUNDATION

Assisted Living Technology - Digital Foundation

TEKTIP: HOW TO MAKE SENIOR LIVING TECHNOLOGY EASY

Assisted Living Technology - Overview